Client:
                            
                            Sunnyside Produce
                        
                    
                    
                        
                            
                                Location:
                            
                            Delta
                        
                    
                    
                        
                            
                                Start Date:
                            
                            June 2024
                        
                    
                 
                
                    For this project, we prepared 40 acres of land for a large greenhouse building, moving 100,000 cubic meters of glacial till. Using bulldozer machine control, we raised the site by 1 meter to ensure the entire area met the required 0.2% grade, with precision accuracy within ±2cm. The grading was crucial to ensure the site was suitable for building and elevated above the flood limits, providing a stable and secure foundation for the greenhouse development.